Church Roof Repair
Work in Progress
Work began on Tuesday 5th May
(Some of these photographs are large so please be patient while they download)
Photographs by K. E. Downie
(Additional photographs will be added as the work progresses)
MOST RECENT UPDATE 3rd OCTOBER 2009
Architect:
Hayton, Lee & Braddock
Stockton Business Centre,
70 Brunswick Street,
Stockton on Tees,
TS18 1DW.
Tel: 01642 345174
Email: info@hlbarchitects.com
Main Contractor:
Wensley Roofing Ltd.,
Station Road,
Chester-le-Street,
Co Durham.
WARNING

SmartWater technology has been applied to all new lead work. Click on logo above for more information.

1. West End May 11th 2009

2. North Nave May 11th 2009

3. South Nave May 11th 2009
_______________________________________________________

4. North West Nave 18th May 2009

5. South Nave & Wensley Vans 18th May 2009

6. Lady Chapel - West Roof 18th May 2009
________________________________________________________
ADDITIONAL PROBLEMS DISCOVERED
(29th May 2009)

7. Rotting timbers at North West Nave

8. Dry Rot at North East Nave

9. Rotting Timbers at North East Nave
___________________________________________________

10, Applying insulation to North Nave - 25th May 2009
11. Removal of slates on North Nave - 25th May 2009

12. Temporary covering to Noth West Nave - 23rd May 2009
__________________________________________________________________

13. Internal scaffold to repair internal timbers - 6th June 2009
14, Repairing internal timbers - 6th June 2009

15. Preparing to repair cross - 6th June 2009
__________________________________________________________

16. Vertical crack up stem of cross 5th June 2009

17. Repair to cross 19th June 2009

18. Repair to base of cross 19th June 2009
19. North nave ridge ready for tiling - 19th June 2009
_______________________________________________________________

20. Sketch showing extent of the problem with rot in the beams

21. Example of construction of beams

22. Carbon fibre rod in place before addition of resin - 22nd June 2009

23. Carbon fibre rod in horizontal beam - 22nd June 2009

24. New timber section in place - 22nd June 2009
____________________________________________________________

25. Partially repaired North Nave - 29th June 2009
26. Work begins on South Nave - 29th June 2009
27. Work on Apse begins - 29th June 2009
___________________________________________________

28. Cross repair completed - 13th July 2009

29. North nave timber repair completed - 13th July 2009
___________________________________________________

30. Repaired stone decoration over clergy vestry - 20th July 2009

31. Opening up vestry valley (the cause of many problems over the years)
20th July 2009

32. Repair to Lady Chapel east valley - 20th July 2009

33. North west nave 30% re-slating completed - 20th July 2009
(using slates from the south nave)

34. Stone chasing-out on clergy vestry - 20th July 2009.
(note how slates were originally chased into the stonework. This extra chasing is now necessary to accomodate the extra thickness of insulation)
___________________________________________________

35. North nave/transept repaired - 27th July 2009
(Compare photos #20-24)

36. North nave truss repaired - 27th July 2009
(Compare photos #20-24)

37. Lady Chapel west roof stripped - 27th July 2009

38. Westmorland slates in transit - 27th July 2009
______________________________________________

39. Nave south/transept rot discovered - 3rd August 2009

40. Nave south/transept prepared for repair - 3rd August 2009

41. Nave south seen from Lady Chapel - 3rd August 2009
_____________________________________________

42. New slates on east Lady Chapel roof - 17th August 2009

43. Guttering renovated, repainted and replaced - 17th August 2009
(All new leadworks have been treated with Smartwater technology - please see top of this page for information on SmartWater)

44. Further problems discovered at nave/Lady Chapel corner - 17th August 2009
____________________________________________________

45. New slates on south nave/transept - 14th September 2009

46. New slates on south nave - 14th September 20009
____________________________________________________

47. New slates on south nave - 21st September 2009

48. Experimental new soak away - 21st September 2009
____________________________________________________
|